BVIEC receives five bids for 2 MW solar and storage project

Following a site visit on December 11, 2019, by twenty-eight global companies, five companies have submitted bids for the Anegada Hybrid Renewable Energy and Battery Storage System Project. BVIEC said the companies who submitted bids and their main characteristics for the project are Advanced Solar Products, MAN-HEG, Power52, Tugliq and Virtual Engineers.

The combined Project capacity will be 2.1 MWdc, with 1.2 MWdc of solar PV and 930 kW-4h BESS.

The Project includes the installation of a Micro-Grid Master Controller which will control the PV, Battery Storage System (BESS) and a backup diesel generator which is currently the sole source of electricity for Anegada.

Source