Puerto Rico’s Energy Bureau has conditionally approved a 100 MW/400 MWh battery energy storage project in Yabucoa under a 20-year agreement with PREPA. The regulator requires the developer to maintain the system’s full four-hour storage capacity throughout the contract, ensuring long-term grid reliability while final interconnection studies are completed.